PK0-005 Tools and Documentation Practice Question

A project manager notices that the project is behind schedule. The planned value (PV) is $50,000, earned value (EV) is $40,000, and actual cost (AC) is $45,000. What is the schedule performance index (SPI) and what does it indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

0.8, behind schedule

SPI = EV / PV = 40,000 / 50,000 = 0.8. An SPI less than 1 indicates the project is behind schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 1.25, ahead of schedule

    Why it's wrong here

    That would be if EV > PV.

  • 0.8, behind schedule

    Why this is correct

    SPI = 0.8, indicating behind schedule.

  • 0.89, behind schedule

    Why it's wrong here

    This is CV/PV incorrectly.

  • 1.0, on schedule

    Why it's wrong here

    SPI = 1 is on schedule.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.