PK0-005 Project Life Cycle Practice Question
Which of the following is an example of a risk response strategy to avoid a risk?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Changing the project scope to eliminate the risk
Avoidance involves changing the project plan to eliminate the risk or protect objectives.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Changing the project scope to eliminate the risk
Why this is correct
Scope change to eliminate the risk is avoidance.
- ✗
Accepting the risk and budgeting for impact
Why it's wrong here
That is acceptance.
- ✗
Purchasing insurance
Why it's wrong here
Insurance is a transfer strategy.
- ✗
Assigning a risk owner
Why it's wrong here
Assigning owner is part of risk management, not a response strategy.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.