Which of the following is an example of a risk response strategy to avoid a risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Changing the project scope to eliminate the risk

Avoidance involves changing the project plan to eliminate the risk or protect objectives.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Changing the project scope to eliminate the risk

    Why this is correct

    Scope change to eliminate the risk is avoidance.

  • Accepting the risk and budgeting for impact

    Why it's wrong here

    That is acceptance.

  • Purchasing insurance

    Why it's wrong here

    Insurance is a transfer strategy.

  • Assigning a risk owner

    Why it's wrong here

    Assigning owner is part of risk management, not a response strategy.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.