Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

Which risk response strategy involves taking action to reduce the probability or impact of a risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Mitigate

Mitigation involves reducing the probability or impact of a risk to an acceptable level.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Accept

    Why it's wrong here

    Acceptance acknowledges the risk without action.

  • Avoid

    Why it's wrong here

    Avoidance eliminates the risk entirely.

  • Mitigate

    Why this is correct

    Correct: mitigation reduces probability or impact.

  • Transfer

    Why it's wrong here

    Transfer shifts the risk to a third party.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.