PK0-005 Project Life Cycle Practice Question
Which risk response strategy involves taking action to reduce the probability or impact of a risk?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Mitigate
Mitigation involves reducing the probability or impact of a risk to an acceptable level.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Accept
Why it's wrong here
Acceptance acknowledges the risk without action.
- ✗
Avoid
Why it's wrong here
Avoidance eliminates the risk entirely.
- ✓
Mitigate
Why this is correct
Correct: mitigation reduces probability or impact.
- ✗
Transfer
Why it's wrong here
Transfer shifts the risk to a third party.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.