Courseiva
Project Life Cycle →easyMultiple Choice

PK0-005 Project Life Cycle Practice Question

Which risk response strategy involves taking action to reduce the probability or impact of a risk?

⚠ Common exam trap

PK0-005 often tests the subtle difference between mitigating and avoiding a risk—candidates may pick 'avoid' thinking it means reducing impact, but avoidance removes the risk entirely by changing the plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Mitigate

Mitigate is the risk response strategy that focuses on reducing either the likelihood or the impact of a risk. In project management (e.g., PMBOK), mitigation involves proactive actions such as implementing additional testing, using redundant components, or providing training to lower the chance of a risk occurring or to lessen its consequences if it does. This is distinct from other strategies that change the risk's probability/impact by other means, such as avoiding the risk entirely or shifting it to a third party.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Accept

    Why it's wrong here

    Acceptance acknowledges a risk and monitors it without changing either its likelihood or its effect, so no mitigating action is taken. It tempts when the exposure sits within tolerance or the cost of treatment exceeds the potential loss, making acceptance a deliberate, documented choice rather than neglect.

  • ✗

    Avoid

    Why it's wrong here

    Avoidance eliminates the risk by removing the activity or asset that creates it, altering scope rather than reducing probability or impact. It tempts when exposure is unacceptable and the underlying process can simply be discontinued, but it is a different strategy from mitigating an ongoing risk.

  • ✓

    Mitigate

    Why this is correct

    Correct: mitigation reduces probability or impact.

  • ✗

    Transfer

    Why it's wrong here

    Transfer shifts the financial consequence to a third party, typically through insurance or contractual indemnity, leaving the probability and technical impact unchanged. It tempts for low-frequency, high-severity exposures where a premium is cheaper than controls, but the risk itself still occurs.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.