PK0-005 Project Life Cycle Practice Question
A project manager receives a change request from a stakeholder. What is the first step the project manager should take?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Perform an impact analysis
The first step is to perform an impact analysis to assess the effects of the change before submission to the CCB.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Submit the change to the change control board
Why it's wrong here
First, impact analysis should be done.
- ✓
Perform an impact analysis
Why this is correct
Impact analysis is the first step in change control.
- ✗
Implement the change immediately
Why it's wrong here
Changes must go through change control.
- ✗
Update the project baseline
Why it's wrong here
Baselines are updated after approval.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.