Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager receives a change request from a stakeholder. What is the first step the project manager should take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform an impact analysis

The first step is to perform an impact analysis to assess the effects of the change before submission to the CCB.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Submit the change to the change control board

    Why it's wrong here

    First, impact analysis should be done.

  • Perform an impact analysis

    Why this is correct

    Impact analysis is the first step in change control.

  • Implement the change immediately

    Why it's wrong here

    Changes must go through change control.

  • Update the project baseline

    Why it's wrong here

    Baselines are updated after approval.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.