Tools and Documentation →mediumMultiple Choice

PK0-005 Tools and Documentation Practice Question

Which document defines the roles and responsibilities of stakeholders in a project and is often presented as a matrix?

⚠ Common exam trap

Many exam-takers confuse the stakeholder register (a list) with the RACI matrix (a matrix of roles and responsibilities), leading them to select Option C instead of the correct matrix-based document.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

RACI matrix

The RACI matrix (Responsible, Accountable, Consulted, Informed) is the correct document because it explicitly defines stakeholder roles and responsibilities in a project and is presented as a matrix format. This aligns with the PMBOK Guide and the PK0-005 exam objectives for Tools and Documentation, where the RACI matrix is the standard tool for clarifying participation levels across project tasks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    RACI matrix

    Why this is correct

    The RACI matrix maps each project task to who is Responsible, Accountable, Consulted and Informed, directly defining stakeholder roles and responsibilities. Its grid format satisfies the stem's "presented as a matrix" constraint, unlike a project charter or communications plan, which describe scope or messaging rather than assigning per-activity accountability.

  • ✗

    Communication plan

    Why it's wrong here

    A communication plan specifies what information is shared, with whom, when and how; it does not assign project roles. It is tempting because it maps stakeholders to information needs, which would be correct when defining reporting cadence and escalation paths rather than accountability.

  • ✗

    Stakeholder register

    Why it's wrong here

    A stakeholder register records stakeholder identification, interests, influence and engagement classification; it does not define role accountability across project activities. It is tempting because it lists stakeholders, which would be correct for engagement planning rather than assigning responsibility for deliverables.

  • ✗

    Project charter

    Why it's wrong here

    The project charter formally authorises the project and names the project manager, but it does not allocate responsibilities across stakeholders in matrix form. It is tempting because it documents high-level roles, which would be correct for project authorisation rather than detailed responsibility assignment.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.