mediumMultiple Choice

PK0-005 Practice Question: A project manager needs to document the process…

A project manager needs to document the process for submitting and approving change requests. Which document should the project manager create?

⚠ Common exam trap

It's easy for candidates to confuse the change management plan with the project charter, mistakenly thinking the charter includes detailed change procedures, when in fact the charter only provides high-level authorization and the change management plan is a separate, detailed document.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Change management plan

The change management plan is the correct document because it specifically defines the process for submitting, reviewing, approving, and tracking change requests. This plan outlines the roles, responsibilities, and procedures for managing changes to project baselines, ensuring that all modifications are controlled and documented.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Change management plan

    Why this is correct

    The change management plan defines how change requests are submitted, evaluated, approved, and documented, directly satisfying the need to record the submission and approval process. It establishes the governance procedures, approval authorities, and required forms, unlike a change log, which merely records individual requests after they occur.

  • ✗

    Risk register

    Why it's wrong here

    The risk register records identified risks, their analysis, owners and responses; it contains no procedure for submitting or approving change requests. It is tempting because both documents support control, yet change requests are handled through the change management plan, with the register tracking only risk.

  • ✗

    Lessons learned

    Why it's wrong here

    Lessons learned capture knowledge and experience for future projects, not the procedural steps for raising, assessing and approving change requests. It is tempting because lessons reports do document process improvements, but the change control process itself belongs in the change management plan.

  • ✗

    Project charter

    Why it's wrong here

    The project charter authorises the project and names the project manager; it does not define how change requests are submitted, evaluated and approved. It is tempting because charters establish governance at a high level, but the detailed change control procedure sits in the change management plan.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.