A project manager is creating the WBS. Which THREE of the following are characteristics of a well-constructed WBS?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Each level represents a smaller detail of the level above

WBS should be deliverable-oriented, decomposed to manageable level, and follow 100% rule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Each level represents a smaller detail of the level above

    Why this is correct

    Correct, decomposition.

  • Deliverable-oriented decomposition

    Why this is correct

    Correct characteristic.

  • Includes all work defined in the project scope

    Why this is correct

    Correct, 100% rule.

  • Organized by project phases

    Why it's wrong here

    WBS is deliverable-oriented, not phase-based.

  • Includes administrative tasks not in scope

    Why it's wrong here

    Should not include out-of-scope work.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.