PK0-005 A project manager is creating the WBS Practice Question
A project manager is creating the WBS. Which THREE of the following are characteristics of a well-constructed WBS?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Each level represents a smaller detail of the level above
WBS should be deliverable-oriented, decomposed to manageable level, and follow 100% rule.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Each level represents a smaller detail of the level above
Why this is correct
Correct, decomposition.
- ✓
Deliverable-oriented decomposition
Why this is correct
Correct characteristic.
- ✓
Includes all work defined in the project scope
Why this is correct
Correct, 100% rule.
- ✗
Organized by project phases
Why it's wrong here
WBS is deliverable-oriented, not phase-based.
- ✗
Includes administrative tasks not in scope
Why it's wrong here
Should not include out-of-scope work.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.