PK0-005 Tools and Documentation Practice Question

An agile team is reviewing their work. Which TWO metrics can be used to track progress within a sprint? (Select TWO).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Burnup chart

Burndown chart shows remaining work over time in a sprint, and burnup chart shows completed work over time. Velocity is a metric across sprints, not within one sprint; product backlog and Kanban board are not metrics.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Product backlog

    Why it's wrong here

    Product backlog is a list of work, not a metric.

  • Burnup chart

    Why this is correct

    Burnup chart tracks completed work within a sprint.

  • Kanban board

    Why it's wrong here

    Kanban board is a visualization tool, not a metric.

  • Velocity

    Why it's wrong here

    Velocity is measured per sprint but is a historical average, not within-sprint tracking.

  • Burndown chart

    Why this is correct

    Burndown chart tracks remaining work within a sprint.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.