PK0-005 Tools and Documentation Practice Question
An agile team is reviewing their work. Which TWO metrics can be used to track progress within a sprint? (Select TWO).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Burnup chart
Burndown chart shows remaining work over time in a sprint, and burnup chart shows completed work over time. Velocity is a metric across sprints, not within one sprint; product backlog and Kanban board are not metrics.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Product backlog
Why it's wrong here
Product backlog is a list of work, not a metric.
- ✓
Burnup chart
Why this is correct
Burnup chart tracks completed work within a sprint.
- ✗
Kanban board
Why it's wrong here
Kanban board is a visualization tool, not a metric.
- ✗
Velocity
Why it's wrong here
Velocity is measured per sprint but is a historical average, not within-sprint tracking.
- ✓
Burndown chart
Why this is correct
Burndown chart tracks remaining work within a sprint.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.