Courseiva
Tools and Documentation →hardMultiple Select

PK0-005 Tools and Documentation Practice Question

An agile team is reviewing their work. Which TWO metrics can be used to track progress within a sprint? (Select TWO).

⚠ Common exam trap

PK0-005 often tests the distinction between sprint-level tracking metrics (burndown/burnup) and broader agile tools or metrics (product backlog, Kanban board, velocity), so candidates must recognize that only burndown and burnup charts are specifically designed to track progress within a single sprint.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Burnup chart

A burnup chart (B) is correct because it tracks the amount of work completed against the total scope over time, letting the team see progress within a sprint and whether scope changes are affecting completion. A burndown chart (E) is correct because it plots remaining work (typically in story points or hours) against time in the sprint, showing whether the team is on track to finish by sprint end. Both are standard sprint-level progress tracking tools in agile. The product backlog (A) is a prioritized list of work items, not a progress metric, and it spans the whole product rather than a single sprint. A Kanban board (C) is a visual workflow management tool that shows work status, not a quantitative progress metric. Velocity (D) measures the average amount of work completed per sprint and is used for release/forecast planning across sprints, not for tracking progress within a single sprint.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Product backlog

    Why it's wrong here

    The product backlog is a prioritised list of pending work owned by the product owner, not a metric, so it cannot measure progress within a sprint. It is tempting because backlog items completed do indicate delivery, but the artefact itself is not a trackable sprint metric.

  • ✓

    Burnup chart

    Why this is correct

    A burnup chart plots completed work against total scope, exposing scope changes that distort a burndown. It tracks sprint progress by showing whether remaining work reflects added or removed stories, satisfying the stem's requirement for a metric measuring progress within a sprint.

  • ✗

    Kanban board

    Why it's wrong here

    A Kanban board visualises workflow and limits work in progress; it is a tool, not a metric, so it cannot quantify sprint progress. It is tempting because teams genuinely use boards to track daily status, but the question asks for measurable metrics such as burndown or velocity.

  • ✗

    Velocity

    Why it's wrong here

    Velocity measures story points completed per sprint, aggregating historical team output rather than tracking progress within the current sprint. It is tempting because it is a genuine agile metric, but it is used for release forecasting and capacity planning, not intra-sprint progress, which burndown charts serve.

  • ✓

    Burndown chart

    Why this is correct

    A burndown chart plots remaining work against time within the sprint, giving the team a daily view of whether they will meet the sprint goal. It satisfies the stem's requirement for a within-sprint progress metric, unlike release-level or cross-sprint measures such as velocity or cumulative flow diagrams.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.