Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project has three activities on the critical path. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. What is the total float for any activity on the critical path?

⚠ Common exam trap

PK0-005 often tests the definitional fact that critical path float is zero, while distracting candidates with the activity durations or their sum as plausible numeric answers.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

0 days

Total float (slack) on the critical path is always zero by definition. The critical path is the longest sequence of dependent activities through the network, and any delay to a critical-path activity directly delays the project finish date. Therefore, activities on the critical path have no scheduling flexibility.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    3 days

    Why it's wrong here

    Three days is Activity B's duration, not a float value; float measures scheduling slack, and critical-path activities have none. It is tempting because it is one of the stem's given numbers, and would be relevant if the question asked for the shortest activity's duration.

  • ✓

    0 days

    Why this is correct

    By definition, activities on the critical path have zero total float; any delay directly extends the project duration. The durations of 5, 3 and 4 days sum to the critical path length, and none of these activities can slip without delaying completion.

  • ✗

    12 days

    Why it's wrong here

    Twelve days is the critical path's total duration (5+3+4), not the float of its activities. It is tempting because summing the durations is the natural first calculation, and that figure would be the answer if the question asked for project duration rather than total float.

  • ✗

    4 days

    Why it's wrong here

    Four days is Activity C's duration, not a float value; float measures scheduling slack, and critical-path activities have none. It is tempting because it is one of the stem's given numbers, and would be relevant if the question asked for the longest single activity's duration.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.