PK0-005 Project Management Concepts Practice Question
In which organizational structure does a project manager have the highest level of authority?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Projectized
In a projectized structure, the project manager has full authority over the project and dedicated team members.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Projectized
Why this is correct
PM has full authority.
- ✗
Balanced matrix
Why it's wrong here
In balanced matrix, authority is shared.
- ✗
Weak matrix
Why it's wrong here
In weak matrix, PM has limited authority.
- ✗
Functional
Why it's wrong here
In functional, PM has little to no authority.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.