A project team is in the storming stage of Tuckman's model. Which of the following behaviors is most likely to be observed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Team members challenge each other's ideas

In the storming stage, team members may have conflicts and disagreements as they assert their opinions and struggle for positions. This is a natural part of team development.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Team members challenge each other's ideas

    Why this is correct

    Storming is characterized by conflict and competition.

  • Team members are polite and avoid conflict

    Why it's wrong here

    This describes the forming stage.

  • Team members work together efficiently

    Why it's wrong here

    This describes the performing stage.

  • Team members focus on completing tasks

    Why it's wrong here

    Task focus increases in norming and performing.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.