A project is in the Closing phase. The project manager has obtained final acceptance of the product from the customer and has transferred the product to operations. Which activity should be performed next as part of closing the project?

⚠ Common exam trap

The trap here is thinking that quality control or risk updates continue into closing, when the focus shifts to administrative and contractual closure.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Archive project documents and release project resources.

In the Closing phase, after final acceptance and transition, the project manager should archive project documents and release project resources. These actions ensure that records are preserved for future reference and that team members are freed for other work. Quality control and risk updates belong to earlier phases, and schedule development is a planning activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Archive project documents and release project resources.

    Why this is correct

    After final product acceptance and transition, the project manager should archive project documents and release resources. Archiving preserves historical data for future projects and audits, while releasing resources allows team members to return to functional or other assignments. These are key activities in the Close Project or Phase process. This step completes the project formally and ensures organizational assets are updated.

  • ✗

    Perform quality control inspections on the final deliverables.

    Why it's wrong here

    Quality control inspections should have been completed before final acceptance. Performing them now would be redundant and could indicate that acceptance was premature. The Closing phase focuses on administrative and contractual closure, not on verifying product quality. The customer has already accepted the product, so further inspections are not the next activity in the closing process.

  • ✗

    Update the risk register with new risks identified during closure.

    Why it's wrong here

    While risks can be identified at any time, the Closing phase is primarily about finalizing all activities. Updating the risk register is more relevant during Monitoring and Controlling. At this stage, the focus is on archiving documents, releasing resources, and obtaining final sign-offs. Adding new risks during closure is not a standard next step and would not complete the project.

  • ✗

    Develop a detailed project schedule for the next phase.

    Why it's wrong here

    Developing a detailed schedule is part of Planning, not Closing. If the project is in Closing, all phases or the project itself are being finalized. Creating a new schedule would be inappropriate unless a new project is being initiated, which is outside the scope of closing the current project. This option confuses planning activities with closing activities.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.