Tools and Documentation →mediumMultiple Choice

PK0-005 Tools and Documentation Practice Question

An agile team uses a tool where they maintain a list of features, enhancements, and bug fixes that are not yet scheduled for a sprint. This list is prioritized by the product owner. What is this list called?

⚠ Common exam trap

PK0-005 often tests the distinction between the product backlog (all unscheduled, prioritized work) and the sprint backlog (committed current-sprint work), catching candidates who assume any backlog is the sprint backlog.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Product backlog

The product backlog is the single, prioritized list of all desired work for the product — features, enhancements, and bug fixes — that are not yet scheduled for a sprint, and it is owned and ordered by the product owner. Items move from the product backlog into the sprint backlog only when selected during sprint planning. Because the question describes an unscheduled, product-owner-prioritized list, the product backlog is the correct answer.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Sprint backlog

    Why it's wrong here

    The sprint backlog holds items the team has already committed to for the current sprint, not the unscheduled, product-owner-prioritised list of features, enhancements and fixes. It is tempting because both are ordered lists of work, and it would be correct when describing the subset selected during sprint planning for delivery in that iteration.

  • ✓

    Product backlog

    Why this is correct

    The product backlog is the prioritised, emergent list of features, enhancements and bug fixes not yet scheduled into a sprint, owned and ordered by the product owner. It satisfies the stem's description of an unscheduled, product-owner-prioritised list.

  • ✗

    Issue log

    Why it's wrong here

    An issue log records problems, impediments and their resolution status during a project; it does not hold the prioritised, unscheduled features, enhancements and bug fixes. It is tempting because defects appear in both, and it would be correct when the requirement is tracking active blockers or issues raised by stakeholders rather than future work.

  • ✗

    Risk register

    Why it's wrong here

    A risk register records identified risks with probability, impact, owner and mitigation responses; it does not hold features, enhancements and bug fixes awaiting sprint scheduling. It is tempting because both are maintained lists with owners, and it would be correct when the requirement is tracking uncertain events that could affect project objectives.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.