Project Management ConceptshardMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

During a project, a stakeholder requests additional features that were not in the original scope. The project manager adds these features without formal change control. This is an example of:

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Scope creep

Scope creep refers to uncontrolled changes or continuous growth in a project's scope, often without proper authorization.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Value engineering

    Why it's wrong here

    Value engineering aims to reduce costs while maintaining functionality.

  • Scope creep

    Why this is correct

    Uncontrolled scope changes without formal approval.

  • Quality assurance

    Why it's wrong here

    Quality assurance focuses on process compliance.

  • Gold plating

    Why it's wrong here

    Gold plating is adding extra features by the team, not necessarily due to stakeholder request.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.