- A
Communication management plan
Why wrong: Communication plan is for info distribution, not staffing.
- B
Project schedule
Why wrong: Schedule may need update but not first.
- C
Resource management plan
Resource plan includes staffing strategies.
- D
Risk register
Why wrong: Risk register might list turnover risk but not the immediate action.
Quick Answer
The answer is the resource management plan. This is the correct document to update first because it formally governs how project resources are acquired, allocated, managed, and released; when a key team member resigns, the plan must be revised to reflect the vacancy and trigger the process for securing a replacement before any other plans can be adjusted. On the CompTIA Project+ PK0-005 exam, this question tests your understanding of the resource management plan’s role as the central source of truth for staffing changes, and a common trap is to mistakenly update the staffing management plan or the project schedule first. To remember, think of the resource management plan as the “who and how” blueprint—when a team member resignation occurs, you update the blueprint before you can reassign tasks or adjust timelines. A useful memory tip is “Resignation first, then reallocation,” meaning the plan itself must be updated before any other resource decisions are made.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During project execution, a key team member resigns. The project manager needs to fill the role quickly. Which document should the project manager update first?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Resource management plan
The resource management plan documents how project resources, including team members, are acquired, allocated, managed, and released. When a key team member resigns, the project manager must first update the resource management plan to reflect the vacancy and initiate the process for acquiring a replacement, ensuring resource needs are clearly defined before adjusting other plans.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Communication management plan
Why it's wrong here
Communication plan is for info distribution, not staffing.
- ✗
Project schedule
Why it's wrong here
Schedule may need update but not first.
- ✓
Resource management plan
Why this is correct
Resource plan includes staffing strategies.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Risk register
Why it's wrong here
Risk register might list turnover risk but not the immediate action.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the misconception that the risk register should be updated first for any unexpected event, but the resignation is a realized issue requiring immediate resource management, not a risk to be logged before action.
Detailed technical explanation
How to think about this question
The resource management plan is part of the project management plan and includes details such as roles and responsibilities, resource calendars, and staff acquisition strategies. In practice, updating this plan first ensures that the project manager formally documents the change in resource availability, which then informs downstream updates to the schedule (e.g., re-baselining tasks) and risk register (e.g., noting the impact of the vacancy). This sequential approach aligns with the PMBOK Guide's process of managing resource changes before adjusting other project documents.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Resource management plan — The resource management plan documents how project resources, including team members, are acquired, allocated, managed, and released. When a key team member resigns, the project manager must first update the resource management plan to reflect the vacancy and initiate the process for acquiring a replacement, ensuring resource needs are clearly defined before adjusting other plans.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.