Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project manager uses a quantitative risk…

A project manager uses a quantitative risk analysis tool that runs thousands of simulations to determine the probability of completing the project by a certain date. Which technique is being used?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Monte Carlo simulation

Monte Carlo simulation uses repeated random sampling to model the probability of different outcomes, commonly used for schedule and cost risk analysis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Decision tree analysis

    Why it's wrong here

    Decision tree analysis evaluates alternative choices under uncertainty.

  • Monte Carlo simulation

    Why this is correct

    Correct. This technique runs many simulations to predict outcomes.

  • Expected monetary value analysis

    Why it's wrong here

    Expected monetary value analysis calculates average outcomes.

  • Sensitivity analysis

    Why it's wrong here

    Sensitivity analysis determines which risks have the most impact.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.