A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Finish-to-Start (FS)

Finish-to-Start (FS) is the most common dependency where the successor cannot start until the predecessor finishes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Finish-to-Start (FS)

    Why this is correct

    Correct: the successor starts only after the predecessor finishes.

  • Start-to-Start (SS)

    Why it's wrong here

    SS means the successor starts after the predecessor starts.

  • Finish-to-Finish (FF)

    Why it's wrong here

    FF means the successor finishes after the predecessor finishes.

  • Start-to-Finish (SF)

    Why it's wrong here

    SF means the successor finishes after the predecessor starts.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.