Courseiva
easyMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project manager is documenting the specific…

A project manager is documenting the specific actions that will be taken to manage and control risks throughout the project. Which document is this?

⚠ Common exam trap

It's easy for candidates to confuse the risk register (which lists individual risks and responses) with the risk management plan (which defines the process for managing all risks), leading them to select the risk register when the question asks for the document that describes the specific actions to manage and control risks.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk management plan

The risk management plan is the document that describes how risk management activities will be structured and performed throughout the project, including specific actions for identifying, analyzing, responding to, and controlling risks. It is a component of the project management plan and provides the methodology, roles, responsibilities, and budgeting for risk management, not the list of individual risks themselves.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Change log

    Why it's wrong here

    Change log records approved changes, not risk management.

  • Risk register

    Why it's wrong here

    Risk register lists identified risks, not the plan for managing them.

  • Issue log

    Why it's wrong here

    Issue log tracks issues that have occurred, not risk management approach.

  • Risk management plan

    Why this is correct

    Risk management plan defines the approach to risk management.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.