Which document is used to track all changes made throughout a project, including their status and impact?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Change log
The change log records all change requests and their disposition.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Configuration management plan
Why it's wrong here
Configuration management plan describes how to manage configuration items, but the change log records changes.
- ✗
Risk register
Why it's wrong here
Risk register tracks risks, not changes.
- ✓
Change log
Why this is correct
The change log is the correct document for tracking changes.
- ✗
Issue log
Why it's wrong here
Issue log tracks problems, not changes.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.