Courseiva
easyMultiple ChoiceObjective-mapped

PK0-005 Practice Question: Which document is used to track all changes made…

Which document is used to track all changes made throughout a project, including their status and impact?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Change log

The change log records all change requests and their disposition.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Configuration management plan

    Why it's wrong here

    Configuration management plan describes how to manage configuration items, but the change log records changes.

  • Risk register

    Why it's wrong here

    Risk register tracks risks, not changes.

  • Change log

    Why this is correct

    The change log is the correct document for tracking changes.

  • Issue log

    Why it's wrong here

    Issue log tracks problems, not changes.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.