PK0-005 Project Life Cycle Practice Question
During project execution, the project manager notices that the team is struggling with communication, and key stakeholders are not receiving timely updates. Which THREE documents should the project manager review to improve the situation? (Select THREE).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Issue log
The communication management plan defines how communications are handled; the stakeholder register identifies stakeholders and their needs; the issue log tracks current problems. The risk register lists risks, not communication issues. The WBS is for scope.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk register
Why it's wrong here
While communication issues could be risks, the risk register does not directly address current communication failures.
- ✓
Issue log
Why this is correct
The issue log tracks current problems, including communication issues.
- ✗
Work Breakdown Structure
Why it's wrong here
The WBS is for scope decomposition, not communication.
- ✓
Communication management plan
Why this is correct
It outlines communication methods, frequency, and responsibilities.
- ✓
Stakeholder register
Why this is correct
It identifies stakeholders and their communication needs.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.