This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Exhibit
Project Status Report - Monthly
Budget:
Planned Value (PV): $120,000
Actual Cost (AC): $130,000
Earned Value (EV): $115,000
Refer to the exhibit. Based on the project status report, what is the cost variance (CV) and what does it indicate?
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
CV = -$15,000; over budget
The cost variance (CV) is calculated as earned value (EV) minus actual cost (AC). From the exhibit, EV = $25,000 and AC = $40,000, so CV = $25,000 - $40,000 = -$15,000. A negative CV indicates the project is over budget, meaning costs have exceeded the value of work performed.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
✗
CV = -$5,000; over budget
Why it's wrong here
Incorrect calculation.
✓
CV = -$15,000; over budget
Why this is correct
Correct calculation and interpretation.
Related concept
Read the scenario before looking for a memorised answer.
✗
CV = -$10,000; over budget
Why it's wrong here
Incorrect calculation; uses PV instead of EV.
✗
CV = $5,000; under budget
Why it's wrong here
Incorrect sign and value.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may misread the exhibit or incorrectly compute CV by subtracting EV from AC (AC - EV) instead of EV - AC, leading to a positive value that falsely suggests under budget performance.
Detailed technical explanation
How to think about this question
Cost variance (CV) is a key performance indicator in earned value management (EVM), calculated as EV - AC. A negative CV means the project has spent more than the value of work accomplished, signaling a cost overrun. In real-world projects, this could trigger corrective actions such as re-estimating remaining costs or reallocating resources to control spending.
KKey Concepts to Remember
Read the scenario before looking for a memorised answer.
Find the constraint that changes the correct option.
Eliminate answers that are true in general but not in this case.
TExam Day Tips
→Watch for words such as best, first, most likely and least administrative effort.
→Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: CV = -$15,000; over budget — The cost variance (CV) is calculated as earned value (EV) minus actual cost (AC). From the exhibit, EV = $25,000 and AC = $40,000, so CV = $25,000 - $40,000 = -$15,000. A negative CV indicates the project is over budget, meaning costs have exceeded the value of work performed.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.