Courseiva
hardMultiple Choice

PK0-005 Practice Question: Refer to the exhibit

Exhibit

Project Status Report - Monthly
Budget:
Planned Value (PV): $120,000
Actual Cost (AC): $130,000
Earned Value (EV): $115,000

Refer to the exhibit. Based on the project status report, what is the cost variance (CV) and what does it indicate?

⚠ Common exam trap

The trap here is that candidates may misread the exhibit or incorrectly compute CV by subtracting EV from AC (AC - EV) instead of EV - AC, leading to a positive value that falsely suggests under budget performance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

CV = -$15,000; over budget

The cost variance (CV) is calculated as earned value (EV) minus actual cost (AC). From the exhibit, EV = $25,000 and AC = $40,000, so CV = $25,000 - $40,000 = -$15,000. A negative CV indicates the project is over budget, meaning costs have exceeded the value of work performed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    CV = -$5,000; over budget

    Why it's wrong here

    The exhibit's earned value figures give a different CV, so this value misreads the data; a negative CV does indicate over budget, but the arithmetic is wrong. It is tempting because the sign and interpretation are right, and this answer would be correct had actual cost exceeded earned value by $5,000.

  • ✓

    CV = -$15,000; over budget

    Why this is correct

    Cost variance is earned value minus actual cost; a negative result of $15,000 means costs exceed the budgeted value of work performed, so the project is over budget. This directly satisfies the stem's request for both the CV figure and its interpretation.

  • ✗

    CV = -$10,000; over budget

    Why it's wrong here

    The exhibit's earned value figures yield a different CV, so this figure is miscalculated; the over-budget interpretation is right but the magnitude is wrong. It is tempting because it pairs the correct direction with a plausible number, and would be correct if AC minus EV genuinely equalled $10,000.

  • ✗

    CV = $5,000; under budget

    Why it's wrong here

    The exhibit shows actual cost exceeding earned value, so CV is negative and the project is over budget, not under. It is tempting because a positive CV does mean under budget, and this would be correct had earned value surpassed actual cost by $5,000.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.