Courseiva
mediumMultiple Select

PK0-005 Practice Question: Which TWO documents are typically created during…

Which TWO documents are typically created during the project initiation phase? (Select TWO.)

⚠ Common exam trap

Candidates often confuse documents created during initiation (project charter, stakeholder register) with those created during planning (risk register, WBS), leading them to select the risk register or WBS as initiation deliverables.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project charter

The project charter is a key document created during project initiation that formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. The stakeholder register is also created during initiation to identify all individuals, groups, or organizations that may impact or be impacted by the project, capturing their interests, expectations, and influence levels.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Risk register

    Why it's wrong here

    The risk register is compiled during planning, once risks are identified and analysed, not at initiation when only the charter and stakeholder register are produced. It is tempting because risk thinking begins early and the register is central to delivery, and it would be correct during planning risk management.

  • ✗

    Work breakdown structure

    Why it's wrong here

    The work breakdown structure decomposes deliverables and is produced during planning, after the charter authorises the project. It is tempting because it is a foundational scope document created early, and it would be correct when planning the scope baseline, but initiation outputs are the charter and stakeholder register.

  • ✓

    Project charter

    Why this is correct

    The project charter is the initiating document that formally authorises the project, names the project manager, and records high-level objectives, scope, and constraints. It is created during initiation, satisfying the stem's requirement for a document produced in that phase.

  • ✗

    Lessons learned

    Why it's wrong here

    Lessons learned are captured throughout and consolidated at closure, so they are not an initiation artefact; initiation yields the project charter and stakeholder register. It is tempting because reviewing prior projects informs the charter, and lessons learned would be correct as a closing or knowledge-transfer output.

  • ✓

    Stakeholder register

    Why this is correct

    The stakeholder register is produced during initiation, once the charter authorises the project and identifies affected parties. It records stakeholders, their interests, influence, and engagement requirements, giving the baseline the stem's initiation phase demands before planning begins.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.