Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project manager is leading a software…

A project manager is leading a software development project. The team has completed the coding phase and is about to begin system testing. The project sponsor requests a demonstration of the software to key stakeholders before testing begins. What should the project manager do?

⚠ Common exam trap

Test-takers frequently think accommodating a stakeholder request is always beneficial and can be done informally, but CompTIA Project+ tests the strict adherence to formal change control procedures to prevent unauthorized scope changes and maintain project governance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board for approval to conduct the demonstration.

Introducing a demonstration after the coding phase constitutes a scope change that could impact the project schedule, resources, and testing timeline. The project manager must follow formal change control procedures by submitting a change request to the change control board (CCB) for approval, ensuring that all impacts are assessed and authorized before proceeding.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Inform the sponsor that the demonstration cannot be accommodated and proceed as planned.

    Why it's wrong here

    Ignoring the sponsor can lead to dissatisfaction.

  • Schedule the demonstration and adjust the project schedule accordingly without formal approval.

    Why it's wrong here

    Unilateral changes violate change control.

  • Submit a change request to the change control board for approval to conduct the demonstration.

    Why this is correct

    This follows proper change management procedures.

  • Delay the start of system testing to accommodate the demonstration without a change request.

    Why it's wrong here

    Delaying testing without approval introduces risk.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.