easyMultiple Choice
PK0-005 Practice Question: A project sponsor wants to formally close a…
A project sponsor wants to formally close a project. Which of the following documents should the project manager prepare to obtain sign-off that the project is complete?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Final project report
The final project report provides the basis for the sponsor or customer to formally accept the project deliverables.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register records engagement and communication details throughout delivery; it carries no acceptance signatures or completion criteria. It is tempting because closure requires confirming stakeholders were managed, yet the formal sign-off document is the final project report or acceptance form recording the sponsor's approval.
- ✗
Lessons learned
Why it's wrong here
Lessons learned captures knowledge for future projects and is produced during closure, but it does not obtain sign-off. It is tempting because it is a closure output, so candidates associate it with the closing process group; the document actually signed to confirm completion is the final project report or formal acceptance.
- ✗
Project charter
Why it's wrong here
The project charter authorises the project at initiation and records high-level objectives; it is not a closure artefact and cannot confirm deliverables were accepted. It is tempting because it is a formal approved document bearing the sponsor's signature, but that signature starts the project rather than closing it.
- ✓
Final project report
Why this is correct
The final project report summarises scope, schedule, cost and outcome performance, providing the sponsor with documented evidence for formal sign-off. It satisfies the stem's closure requirement, unlike the charter or business case, which belong to earlier phases.
About these practice questions
This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.