easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project sponsor wants to formally close a…
A project sponsor wants to formally close a project. Which of the following documents should the project manager prepare to obtain sign-off that the project is complete?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Final project report
The final project report provides the basis for the sponsor or customer to formally accept the project deliverables.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register is used throughout the project but not for final acceptance.
- ✗
Lessons learned
Why it's wrong here
Lessons learned are a closure deliverable but are not used for obtaining sign-off.
- ✗
Project charter
Why it's wrong here
The project charter is created during initiation and is not used for closure sign-off.
- ✓
Final project report
Why this is correct
The final project report summarizes project performance and is used to obtain formal acceptance.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.