During project execution, a stakeholder requests a new feature that was not included in the original scope. The project manager initiates a change request. What is the next step in the integrated change control process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Evaluate the impact on the triple constraint
After a change request is submitted, the next step is to evaluate its impact on the triple constraint (time, cost, scope) before sending it to the Change Control Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the project plan immediately
Why it's wrong here
Updating the plan happens only after approval.
- ✓
Evaluate the impact on the triple constraint
Why this is correct
Correct. Impact analysis must be performed before CCB review.
- ✗
Reject the request to prevent scope creep
Why it's wrong here
Rejection without analysis is not part of the formal process.
- ✗
Send the request directly to the Change Control Board
Why it's wrong here
Impact evaluation should precede CCB review.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.