hardMultiple SelectObjective-mapped
PK0-005 Practice Question: Which TWO of the following are typical activities…
Which TWO of the following are typical activities in the Closing phase of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Archive project documents
Closing phase activities include finalizing project reports, archiving documents, and obtaining formal acceptance. Conducting procurements happens in Executing, and developing the project charter is in Initiating.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Develop project charter
Why it's wrong here
The charter is created in Initiating.
- ✓
Archive project documents
Why this is correct
Archiving project information is a key closing activity.
- ✗
Conduct procurements
Why it's wrong here
Conduct procurements is an Executing process.
- ✓
Obtain formal acceptance of the final product
Why this is correct
Formal acceptance is a crucial part of closing.
- ✗
Create the project schedule
Why it's wrong here
The schedule is developed in Planning.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.