PK0-005 Practice Question: Which THREE activities are typically performed…
Which THREE activities are typically performed during the execution phase of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Perform quality assurance
Options A, B, and D are correct. Execution phase activities include performing quality assurance, managing stakeholder engagement, and directing and managing project work. Option C is incorrect because monitoring project risks is part of monitoring and controlling. Option E is incorrect because developing the project charter is done in the initiation phase.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Perform quality assurance
Why this is correct
Execution phase.
- ✓
Manage stakeholder engagement
Why this is correct
Execution phase.
- ✗
Monitor project risks
Why it's wrong here
Monitoring and controlling.
- ✓
Direct and manage project work
Why this is correct
Core execution activity.
- ✗
Develop the project charter
Why it's wrong here
Initiation phase.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.