Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

A project manager is preparing to close out a construction project. The final deliverable was accepted by the customer two weeks ago, but several team members have already been reassigned to a new initiative. The project manager still needs to obtain formal sign-off from the customer, archive project documents, and release remaining resources. Which activity should the project manager complete FIRST in the closing phase?

⚠ Common exam trap

The trap here is assuming that administrative closing tasks like archiving can begin as soon as the deliverable is handed over, when in fact formal acceptance must be documented first.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Obtain formal acceptance and sign-off of the final deliverable from the customer

Formal acceptance and sign-off of the final deliverable is the gateway activity in the closing phase. Without documented customer acceptance, the project cannot be declared complete, and activities such as archiving, releasing resources, and capturing lessons learned would rest on an unverified outcome. Securing sign-off first ensures all remaining closing activities reflect a confirmed, accepted deliverable and protects the project manager from contractual or payment disputes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Archive all project documents and lessons learned in the organizational repository

    Why it's wrong here

    Archiving documents and lessons learned is a valid closing activity, but it should not be the first step. Formal acceptance must be obtained and confirmed before the project manager can consider the project complete and proceed to archive records. Performing archival work before securing final sign-off risks recording incomplete or unverified project outcomes, and the customer could still raise objections that would invalidate the archived materials.

  • ✗

    Conduct a lessons learned session with the remaining stakeholders

    Why it's wrong here

    Lessons learned capture is valuable, but it is more meaningful once the project outcome is confirmed. Holding the session before formal acceptance means the team may discuss an outcome that is not yet validated, and any late customer feedback could change the conclusions. The project manager should first obtain sign-off, then capture lessons learned with accurate, complete information about the final accepted result.

  • ✓

    Obtain formal acceptance and sign-off of the final deliverable from the customer

    Why this is correct

    Formal acceptance of the final deliverable is the trigger that allows the project to move into closing. Until the customer provides documented sign-off, the project cannot be considered complete, and contractual or payment obligations may remain open. The project manager should secure this acceptance first so that subsequent activities such as archiving, releasing resources, and capturing lessons learned reflect a verified, accepted outcome rather than an unconfirmed one.

  • ✗

    Release all remaining project team members and close their assignments

    Why it's wrong here

    Releasing team members is part of closing, but doing it before formal acceptance is risky. If the customer rejects the deliverable or requests rework, the project manager would need those resources back, and reassigning them prematurely could cause delays and additional cost. Resource release should follow confirmed acceptance so the team remains available to address any final acceptance-related issues or corrections.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.