Courseiva
easyMultiple ChoiceObjective-mapped

PK0-005 Control Costs Practice Question

A project manager notices that project costs are consistently exceeding the budget. Which process should the project manager use to address this issue?

⚠ Common exam trap

Candidates often select Plan Cost Management because they think a better plan is needed, but since the project is already in execution, the appropriate process to address the overruns is Control Costs, which involves monitoring, analyzing variances, and taking corrective actions.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Control Costs

The correct process is Control Costs (B) because it is the process of monitoring the status of project costs and managing changes to the cost baseline. When costs consistently exceed the budget, the project manager uses Control Costs to analyze cost variances, forecast future cost overruns, and take corrective actions to bring costs back within the approved budget. This process operates in the Monitoring and Controlling process group and directly addresses ongoing cost issues, unlike Plan Cost Management, which is a planning process that sets the framework before execution begins.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Determine Budget

    Why it's wrong here

    Determine Budget is a planning process that aggregates the estimated costs of individual activities to establish a cost baseline. It does not address ongoing cost overruns during execution.

  • Control Costs

    Why this is correct

    Control Costs is the correct process because it monitors cost performance, analyzes variances, and implements corrective actions to manage budget overruns in real time.

  • Plan Cost Management

    Why it's wrong here

    Plan Cost Management is a planning process that defines how costs will be planned, structured, and controlled. It sets the policies and procedures but does not directly address existing cost overruns.

  • Estimate Costs

    Why it's wrong here

    Estimate Costs is a planning process that develops approximations of the monetary resources needed to complete project activities. It does not handle cost overruns during execution.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.