During project execution, a team member identifies a problem that has already occurred and is affecting the project schedule. The project manager should document this in which of the following?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Issue log
An issue is a current problem that has occurred, as opposed to a risk which is a future uncertain event. Issues are documented in the issue log.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Lessons learned register
Why it's wrong here
Lessons learned are documented after the fact, not for immediate issues.
- ✗
Change log
Why it's wrong here
The change log records approved changes, not issues.
- ✓
Issue log
Why this is correct
Correct. The issue log tracks current problems that have occurred.
- ✗
Risk register
Why it's wrong here
The risk register is for uncertain future events, not current problems.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.