PK0-005 Project Life Cycle Practice Question
A project manager needs to communicate project progress to stakeholders who have low power and high interest. Which of the following is the most appropriate communication method?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Regular email updates
Low power, high interest stakeholders should be kept informed, so regular email updates are appropriate.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ad-hoc phone calls
Why it's wrong here
Ad-hoc may not be sufficient for high interest stakeholders.
- ✓
Regular email updates
Why this is correct
Regular updates keep informed stakeholders engaged.
- ✗
Project dashboard posted on the wall
Why it's wrong here
Dashboards are good but may not be accessible to all.
- ✗
Formal presentation to executives
Why it's wrong here
Executives have high power.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.