Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager needs to communicate project progress to stakeholders who have low power and high interest. Which of the following is the most appropriate communication method?

⚠ Common exam trap

PK0-005 often tests the power/interest grid by swapping communication methods between quadrants; candidates must remember that low-power, high-interest stakeholders need regular but low-effort updates like emails, not meetings or presentations.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Regular email updates

Stakeholders with low power and high interest are kept informed because they care deeply but cannot influence project decisions. Regular email updates are an efficient, low-cost way to provide them with consistent information without over-engaging them. This matches the 'keep informed' strategy in the power/interest grid.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Ad-hoc phone calls

    Why it's wrong here

    Ad-hoc phone calls give no repeatable, documented record of progress, so low-power, high-interest stakeholders cannot track status consistently. They suit urgent, informal one-to-one updates, but this quadrant needs regular, structured reporting such as status reports or dashboards.

  • ✓

    Regular email updates

    Why this is correct

    Regular email updates suit low-power, high-interest stakeholders because they need frequent, digestible progress information without demanding intensive engagement. Email delivers scheduled, asynchronous communication that keeps this group informed and satisfied, matching their high interest while respecting their limited influence over project decisions. More interactive methods would over-serve stakeholders who cannot affect outcomes.

  • ✗

    Project dashboard posted on the wall

    Why it's wrong here

    A wall dashboard is passive and location-bound, so remote or distributed low-power, high-interest stakeholders may never see current progress. It suits co-located teams wanting visible, continuously updated metrics, but this quadrant needs actively distributed regular reporting.

  • ✗

    Formal presentation to executives

    Why it's wrong here

    A formal executive presentation targets high-power stakeholders who make decisions; low-power, high-interest stakeholders need routine information, not governance-level briefings. It would be correct for keeping senior sponsors informed or securing executive approval at key milestones.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.