PK0-005 Project Life Cycle Practice Question
A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Implement the change and update the project baselines
After approval, the change must be implemented and project baselines (scope, schedule, cost) updated to reflect the approved change.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Document the change in the lessons learned
Why it's wrong here
Lessons learned are captured later, not the immediate next step.
- ✓
Implement the change and update the project baselines
Why this is correct
Correct: Approved changes are implemented and baselines updated.
- ✗
Reject the change and inform the requester
Why it's wrong here
The change was approved, not rejected.
- ✗
Update the risk register
Why it's wrong here
Risk register may be updated, but the primary next step is to implement and update baselines.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.