Courseiva
Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Implement the change and update the project baselines

After approval, the change must be implemented and project baselines (scope, schedule, cost) updated to reflect the approved change.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Document the change in the lessons learned

    Why it's wrong here

    Lessons learned are captured at project closure or phase gates, not immediately after CCB approval, so documenting there delays the required update to the change log, schedule and baseline. It is tempting because recording what happened aids future projects, but the approved change must first be integrated into the plan.

  • ✓

    Implement the change and update the project baselines

    Why this is correct

    CCB approval authorises the change, so the next action is executing the approved work and revising the affected project baselines—scope, schedule and cost—to reflect it. Baselines must be updated so subsequent performance measurement and variance analysis compare against the approved revised plan.

  • ✗

    Reject the change and inform the requester

    Why it's wrong here

    Rejecting the change contradicts the CCB's approval, which already authorised it; the requester should instead be informed of acceptance and the change implemented. It is tempting because rejection is a valid CCB outcome, but that decision point has passed once approval is granted.

  • ✗

    Update the risk register

    Why it's wrong here

    Updating the risk register records new threats arising from the approved change, but it is not the immediate next step; the change must first be formally recorded and baselined before downstream documents are revised. It is tempting because risk reassessment genuinely follows approved scope changes, just later in the process.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.