Which TWO of the following are risk identification techniques commonly used in project management? (Choose two.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
SWOT analysis
Common risk identification techniques include brainstorming, Delphi technique, SWOT analysis, and assumptions analysis.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
SWOT analysis
Why this is correct
Correct. SWOT analysis identifies risks from strengths, weaknesses, opportunities, and threats.
- ✗
Crashing
Why it's wrong here
Crashing is a schedule compression technique.
- ✓
Brainstorming
Why this is correct
Correct. Brainstorming is a group technique to generate risks.
- ✗
Fast-tracking
Why it's wrong here
Fast-tracking is a schedule compression technique.
- ✗
Monte Carlo simulation
Why it's wrong here
Monte Carlo simulation is a quantitative analysis technique, not identification.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.