Courseiva
easyMultiple SelectObjective-mapped

PK0-005 Practice Question: Which TWO of the following are risk…

Which TWO of the following are risk identification techniques commonly used in project management? (Choose two.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

SWOT analysis

Common risk identification techniques include brainstorming, Delphi technique, SWOT analysis, and assumptions analysis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • SWOT analysis

    Why this is correct

    Correct. SWOT analysis identifies risks from strengths, weaknesses, opportunities, and threats.

  • Crashing

    Why it's wrong here

    Crashing is a schedule compression technique.

  • Brainstorming

    Why this is correct

    Correct. Brainstorming is a group technique to generate risks.

  • Fast-tracking

    Why it's wrong here

    Fast-tracking is a schedule compression technique.

  • Monte Carlo simulation

    Why it's wrong here

    Monte Carlo simulation is a quantitative analysis technique, not identification.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.