Courseiva
Tools and Documentation →mediumMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project manager notices that the actual cost (AC) is $50,000, the earned value (EV) is $45,000, and the planned value (PV) is $55,000. Which statement is true regarding schedule and cost performance?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The project is behind schedule and over budget.

Schedule variance (SV) = EV - PV = $45,000 - $55,000 = -$10,000 (negative, behind schedule). Cost variance (CV) = EV - AC = $45,000 - $50,000 = -$5,000 (negative, over budget).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The project is ahead of schedule and over budget.

    Why it's wrong here

    EV ($45,000) is below PV ($55,000), so the project is behind schedule, not ahead. AC ($50,000) exceeds EV ($45,000), confirming it is over budget. The cost half is right, but the schedule half misreads the SV calculation.

  • ✓

    The project is behind schedule and over budget.

    Why this is correct

    With EV ($45,000) below PV ($55,000), the schedule performance index is 0.82, confirming the project is behind schedule. With EV below AC ($50,000), the cost performance index is 0.90, confirming it is over budget. Both constraints in the stem are therefore satisfied by this statement.

  • ✗

    The project is behind schedule and under budget.

    Why it's wrong here

    EV ($45,000) is below PV ($55,000), correctly indicating the project is behind schedule. However, AC ($50,000) exceeds EV ($45,000), so it is over budget, not under. The schedule half is right; the cost half misreads the CV calculation.

  • ✗

    The project is ahead of schedule and under budget.

    Why it's wrong here

    With EV ($45,000) below PV ($55,000) and AC ($50,000) exceeding EV, the project is behind schedule and over budget. This option inverts both indices. It would be true only if EV exceeded PV and AC fell below EV, which the figures contradict.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.