PK0-005 Tools and Documentation Practice Question
In an Agile project, the team uses story points to estimate effort. During sprint planning, they select user stories from the product backlog and assign them to the sprint. What is the resulting list of items committed for the sprint called?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Sprint backlog
The sprint backlog is the set of product backlog items selected for the sprint, along with a plan for delivering them. The product backlog is the full list of requirements; burndown/burnup charts track progress.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Product backlog
Why it's wrong here
The product backlog contains all desired features for the product, not just those for a single sprint.
- ✗
Burndown chart
Why it's wrong here
A burndown chart tracks remaining work, not the list of items.
- ✗
Burnup chart
Why it's wrong here
A burnup chart shows completed work over time.
- ✓
Sprint backlog
Why this is correct
The sprint backlog includes items committed for the current sprint.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.