Courseiva
Tools and DocumentationmediumMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project manager is reviewing the schedule performance and finds that the earned value (EV) is $50,000 and the planned value (PV) is $60,000. What does this indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is behind schedule

Schedule variance (SV) = EV - PV = $50,000 - $60,000 = -$10,000. A negative SV means the project is behind schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is on schedule

    Why it's wrong here

    SV is negative, so not on schedule.

  • The project is over budget

    Why it's wrong here

    SV is a schedule indicator, not cost.

  • The project is behind schedule

    Why this is correct

    Correct. Negative SV means behind schedule.

  • The project is ahead of schedule

    Why it's wrong here

    A positive SV would indicate ahead of schedule; this is negative.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.