hardMultiple Choice

PK0-005 Practice Question: A project manager notices that a key team member…

A project manager notices that a key team member is frequently pulled away to work on another priority project, causing delays. This situation is an example of which type of constraint?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Resource constraint

Resource constraints refer to limited availability of personnel, equipment, or materials. This scenario describes a resource constraint due to limited availability of a key person.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Mandatory dependency

    Why it's wrong here

    Mandatory dependencies are contractually or legally required activity sequences, such as needing a foundation before framing. The delay stems from shared personnel availability, which is a resource constraint. Mandatory dependency would fit if the stem described a hard technical or contractual ordering.

  • ✓

    Resource constraint

    Why this is correct

    The team member's availability is limited by competing demands from another project, which is a resource constraint: a restriction on people, equipment, or materials. Scope, time, and cost constraints concern deliverables, schedule, and budget rather than shared staffing.

  • ✗

    Technical constraint

    Why it's wrong here

    A technical constraint concerns limitations of technology, tools or design standards, not staffing. The team member's competing allocation is a resource constraint. Technical constraints would be correct if, for example, a platform's capability restricted how work could proceed.

  • ✗

    Discretionary dependency

    Why it's wrong here

    A discretionary dependency is a choice-based scheduling relationship between activities, not a resourcing conflict. Resource contention across projects is a resource constraint. Discretionary dependencies would be correct when sequencing is optional, such as preferred ordering based on best practise rather than logic.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.