Courseiva
easyMultiple ChoiceObjective-mapped

PK0-005 A project is in the planning phase Practice Question

A project is in the planning phase. The project manager is working with the team to break down the project deliverables into smaller, more manageable components. Which process is being performed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Create WBS

Creating the Work Breakdown Structure (WBS) is the process of subdividing project deliverables into smaller components, which occurs during planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Estimate Costs

    Why it's wrong here

    Estimating costs comes after WBS creation.

  • Create WBS

    Why this is correct

    The WBS decomposes deliverables into work packages.

  • Develop Schedule

    Why it's wrong here

    Develop Schedule involves sequencing activities, not breaking down deliverables.

  • Identify Risks

    Why it's wrong here

    Risk identification is a separate process.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.