easyMultiple ChoiceObjective-mapped
PK0-005 A project is in the planning phase Practice Question
A project is in the planning phase. The project manager is working with the team to break down the project deliverables into smaller, more manageable components. Which process is being performed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Create WBS
Creating the Work Breakdown Structure (WBS) is the process of subdividing project deliverables into smaller components, which occurs during planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Estimate Costs
Why it's wrong here
Estimating costs comes after WBS creation.
- ✓
Create WBS
Why this is correct
The WBS decomposes deliverables into work packages.
- ✗
Develop Schedule
Why it's wrong here
Develop Schedule involves sequencing activities, not breaking down deliverables.
- ✗
Identify Risks
Why it's wrong here
Risk identification is a separate process.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.