PK0-005 Project Management Concepts Practice Question

During project execution, a key stakeholder requests a new feature that was not in the original scope. The project manager is concerned about the impact on the schedule and budget. This is an example of:

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Scope creep

Scope creep refers to uncontrolled changes to project scope. Gold plating is adding features without request. Risk is an uncertain event. Change control is the process to manage changes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scope creep

    Why this is correct

    An unauthorized addition to scope is scope creep.

  • Risk management

    Why it's wrong here

    This is not a risk event; it's a change.

  • Gold plating

    Why it's wrong here

    Gold plating is adding extras without request.

  • Change control

    Why it's wrong here

    Change control is the process to manage the change.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.