Question 488 of 500
Project Life Cycle PhaseshardMultiple ChoiceObjective-mapped

Quick Answer

The correct first action is to conduct a root cause analysis to identify the reasons for the cost and schedule variances. This is because corrective actions for cost and schedule variances must be based on understanding why the variances occurred; jumping to solutions without diagnosis risks addressing symptoms rather than root problems. On the CompTIA Project+ PK0-005 exam, this scenario tests your grasp of the monitoring and controlling process, where root cause analysis is the mandatory first step before implementing any corrective or preventive action. A common trap is choosing to immediately reallocate resources or re-baseline the plan, but the exam emphasizes that you cannot fix what you do not understand. Remember the memory tip: “Diagnose before you prescribe”—always identify the cause of the variance first to ensure your corrective actions are targeted and effective.

PK0-005 Project Life Cycle Phases Practice Question

This PK0-005 practice question tests your understanding of project life cycle phases. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are a project manager for a construction project. During the monitoring and controlling phase, you review the project performance and find that the earned value (EV) is $50,000, the actual cost (AC) is $60,000, and the planned value (PV) is $55,000. The project is behind schedule and over budget. The project team is demotivated due to the delays. The customer has expressed concerns about project progress. The project contract includes a penalty clause for missed milestones. Which of the following actions should you take first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Conduct a root cause analysis to identify reasons for variances

Root cause analysis is the first step in addressing performance variances. Once the causes are known, the project manager can develop an appropriate corrective action plan.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Implement additional quality control measures

    Why it's wrong here

    Quality control does not directly address cost and schedule variances.

  • Request a change order to increase the budget

    Why it's wrong here

    Increasing budget may be necessary, but the first step is to understand the root cause of the variances.

  • Conduct a root cause analysis to identify reasons for variances

    Why this is correct

    Understanding why the project is over budget and behind schedule is critical before taking corrective action.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Immediately notify the customer about the delays

    Why it's wrong here

    While communication is important, notifying without analysis may cause unnecessary alarm; root cause analysis should come first.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Life Cycle Phases — This question tests Project Life Cycle Phases — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Conduct a root cause analysis to identify reasons for variances — Root cause analysis is the first step in addressing performance variances. Once the causes are known, the project manager can develop an appropriate corrective action plan.

What should I do if I get this PK0-005 question wrong?

Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During the monitoring and controlling phase, a project manager receives a status report indicating the CPI is 0.8 and SPI is 0.9. Which action should the project manager take next?

medium
  • A.Celebrate because both indices are above 0.7
  • B.Update the project management plan to reflect the variances
  • C.Analyze the variances and determine corrective actions
  • D.Immediately request more budget from the sponsor

Why C: A CPI of 0.8 means the project is over budget, and an SPI of 0.9 means it is behind schedule. The project manager should analyze the root cause of these variances and consider corrective actions.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.