hardMultiple ChoiceObjective-mapped
PK0-005 A project manager for a construction project Practice Question
You are a project manager for a construction project. During the monitoring and controlling phase, you review the project performance and find that the earned value (EV) is $50,000, the actual cost (AC) is $60,000, and the planned value (PV) is $55,000. The project is behind schedule and over budget. The project team is demotivated due to the delays. The customer has expressed concerns about project progress. The project contract includes a penalty clause for missed milestones. Which of the following actions should you take first?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Conduct a root cause analysis to identify reasons for variances
Root cause analysis is the first step in addressing performance variances. Once the causes are known, the project manager can develop an appropriate corrective action plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Implement additional quality control measures
Why it's wrong here
Quality control does not directly address cost and schedule variances.
- ✗
Request a change order to increase the budget
Why it's wrong here
Increasing budget may be necessary, but the first step is to understand the root cause of the variances.
- ✓
Conduct a root cause analysis to identify reasons for variances
Why this is correct
Understanding why the project is over budget and behind schedule is critical before taking corrective action.
- ✗
Immediately notify the customer about the delays
Why it's wrong here
While communication is important, notifying without analysis may cause unnecessary alarm; root cause analysis should come first.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. During the monitoring and controlling phase, a project manager receives a status report indicating the CPI is 0.8 and SPI is 0.9. Which action should the project manager take next?
medium- A.Celebrate because both indices are above 0.7
- B.Update the project management plan to reflect the variances
- ✓ C.Analyze the variances and determine corrective actions
- D.Immediately request more budget from the sponsor
Why C: A CPI of 0.8 means the project is over budget, and an SPI of 0.9 means it is behind schedule. The project manager should analyze the root cause of these variances and consider corrective actions.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.