Question 231 of 500
Project Management ConceptseasyMultiple ChoiceObjective-mapped

Quick Answer

The answer is 8 days. This is correct because the PERT three-point estimate formula calculates a weighted average using (Optimistic + 4×Most Likely + Pessimistic) / 6, which for the given estimates of 4, 7, and 16 days yields (4 + 28 + 16) / 6 = 48 / 6 = 8 days. The formula is designed to account for uncertainty in tasks with no historical data by giving the most likely estimate four times the weight of the optimistic and pessimistic values, producing a more realistic expected duration. On the CompTIA Project+ PK0-005 exam, this question tests your ability to apply the PERT technique for estimating activity durations under uncertainty, often appearing in scenario-based questions where you must distinguish it from simple averaging or triangular distribution. A common trap is forgetting to multiply the most likely estimate by four or incorrectly dividing by three instead of six. To remember the formula, think “PERT = (O + 4M + P) / 6” — the number 4 and 6 rhyme, helping you recall the weighting and divisor.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is estimating the duration of a task that has never been done before. The team provides three estimates: optimistic (4 days), most likely (7 days), and pessimistic (16 days). Using the PERT three-point estimate formula, what is the expected duration?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "most likely"

    Why it matters: Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

  • Clue: "never"

    Why it matters: Absolute qualifier. True only if the statement has zero exceptions — be cautious of options that seem obvious but break down in edge cases.

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

8 days

The PERT three-point estimate formula is (Optimistic + 4×Most Likely + Pessimistic) / 6. Plugging in the values: (4 + 4×7 + 16) / 6 = (4 + 28 + 16) / 6 = 48 / 6 = 8 days. This weighted average accounts for uncertainty in tasks with no historical data, giving more weight to the most likely estimate.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 9 days

    Why it's wrong here

    9 is the simple average, not PERT.

  • 8 days

    Why this is correct

    Correct PERT calculation.

    Clue confirmation

    The clue words "most likely", "never" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 7 days

    Why it's wrong here

    7 is the most likely estimate only.

  • 10 days

    Why it's wrong here

    10 is the average of optimistic and pessimistic.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the PERT formula by including a distractor that is the simple arithmetic mean (9 days), tempting candidates who forget the weighted 4× multiplier for the most likely estimate.

Detailed technical explanation

How to think about this question

The PERT (Program Evaluation and Review Technique) formula derives from a beta distribution, which models task durations with skew. The standard deviation is (Pessimistic - Optimistic) / 6 = (16-4)/6 = 2 days, giving a variance of 4 days². In practice, this allows the project manager to calculate confidence intervals (e.g., ±1σ gives ~68% probability the task finishes between 6 and 10 days).

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 8 days — The PERT three-point estimate formula is (Optimistic + 4×Most Likely + Pessimistic) / 6. Plugging in the values: (4 + 4×7 + 16) / 6 = (4 + 28 + 16) / 6 = 48 / 6 = 8 days. This weighted average accounts for uncertainty in tasks with no historical data, giving more weight to the most likely estimate.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "most likely", "never". Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.