PK0-005 Project Life Cycle Practice Question
A project manager identifies a risk that a key team member might leave during the project. To reduce the impact, she cross-trains other team members. Which risk response strategy is being applied?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Mitigate
Mitigation reduces the probability or impact of a risk. Cross-training reduces impact.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Accept
Why it's wrong here
Accept means acknowledging the risk without proactive action.
- ✗
Avoid
Why it's wrong here
Avoid eliminates the risk entirely.
- ✗
Transfer
Why it's wrong here
Transfer shifts the risk to a third party.
- ✓
Mitigate
Why this is correct
Cross-training reduces the impact of losing a team member.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.