PK0-005 Project Management Concepts Practice Question

In which organizational structure does the project manager have the least authority over project resources?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Functional

In a functional structure, resources belong to functional managers, and the PM has limited authority. In projectized, the PM has full authority. Matrix structures are in between.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Projectized

    Why it's wrong here

    PM has full authority in projectized.

  • Functional

    Why this is correct

    PM has limited authority; resources are controlled by functional managers.

  • Balanced matrix

    Why it's wrong here

    PM shares authority with functional manager.

  • Strong matrix

    Why it's wrong here

    PM has more authority than functional manager.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.