PK0-005 Project Life Cycle Practice Question
A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
High power, high interest
Stakeholders with high power and high interest should be managed closely as they have significant influence and are highly interested in the project's outcome.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Low power, low interest
Why it's wrong here
Low power, low interest stakeholders should be monitored with minimal effort.
- ✗
Low power, high interest
Why it's wrong here
Low power, high interest stakeholders should be kept informed.
- ✓
High power, high interest
Why this is correct
These stakeholders require the most attention and should be managed closely.
- ✗
High power, low interest
Why it's wrong here
High power, low interest stakeholders should be kept satisfied.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.