Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?

⚠ Common exam trap

The trap is mixing up the 'keep satisfied' and 'manage closely' quadrants; candidates often pick high power/low interest because they focus only on power, but the question asks for the group requiring the closest management, which is high power AND high interest.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

High power, high interest

On the power/interest grid, stakeholders with high power and high interest are the key players who must be managed closely, because they can significantly influence the project and care deeply about its outcome. This quadrant requires the most engagement, frequent communication, and proactive management.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Low power, low interest

    Why it's wrong here

    Low power, low interest stakeholders are monitored with minimal effort, not managed closely; they neither influence outcomes nor care about them. It is tempting to over-engage everyone, but the grid reserves manage-closely for those combining high power with high interest.

  • ✗

    Low power, high interest

    Why it's wrong here

    Low power, high interest stakeholders are kept informed, not managed closely; their interest is high but their authority to affect decisions is limited. It is tempting because their enthusiasm invites engagement, yet manage-closely demands high power alongside high interest.

  • ✓

    High power, high interest

    Why this is correct

    Stakeholders rated high on both power and interest demand the closest engagement because they can significantly affect project outcomes and care deeply about results. The manage-closely quadrant therefore receives frequent, detailed communication and active involvement to sustain their support.

  • ✗

    High power, low interest

    Why it's wrong here

    High power, low interest stakeholders are kept satisfied, not managed closely; their power can derail the project but they lack engagement. It is tempting because their influence is significant, yet the manage-closely quadrant requires both high power and high interest to warrant active, ongoing engagement.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.