In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$1,000 per day

Crash cost per day = (crash cost - normal cost) / (normal duration - crash duration). Assuming normal cost is zero incremental, crash cost per day = $3,000 / (10-7) = $1,000 per day.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $1,000 per day

    Why this is correct

    Correct: $3,000 / 3 days = $1,000 per day.

  • $500 per day

    Why it's wrong here

    Incorrect calculation.

  • $3,000 per day

    Why it's wrong here

    Incorrect calculation.

  • $300 per day

    Why it's wrong here

    Incorrect calculation.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.