Courseiva
Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Obtain formal acceptance from the sponsor

During closure, obtaining formal acceptance from the sponsor and archiving project documents are key activities. Releasing resources and contract closure are also part of closure, but the question asks for two. The correct answers are formal acceptance and archiving documents.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Develop the risk register

    Why it's wrong here

    The risk register is developed during planning.

  • Obtain formal acceptance from the sponsor

    Why this is correct

    Formal acceptance is a key closure activity.

  • Conduct feasibility study

    Why it's wrong here

    Feasibility study is done during initiation.

  • Create the project charter

    Why it's wrong here

    The charter is created during initiation.

  • Archive project documents

    Why this is correct

    Archiving documents is part of closure.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.