Courseiva
Project Life Cycle →mediumMultiple Select

PK0-005 Project Life Cycle Practice Question

A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)

⚠ Common exam trap

PK0-005 often tests the distinction between process groups; the trap is selecting planning or initiating activities (risk register, charter, feasibility study) as closure activities because they are familiar project documents.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Obtain formal acceptance from the sponsor

Option B is correct because obtaining formal acceptance from the sponsor is a key project closure activity; the sponsor (or customer) must formally sign off that deliverables meet requirements, which is required before the project can be officially closed. Option E is correct because archiving project documents is part of closing the project; lessons learned, final reports, and project records are collected, indexed, and stored for future reference and organizational process assets. Option A is incorrect because the risk register is developed during project planning and updated throughout execution, not created at closure. Option C is incorrect because a feasibility study is performed during the pre-project or initiation phase to determine whether the project is viable. Option D is incorrect because the project charter is created during initiation to formally authorize the project, not during closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Develop the risk register

    Why it's wrong here

    The risk register is developed during planning and maintained throughout execution, not created at closure. It is tempting because closure does involve reviewing risks and lessons learned, and compiling a risk register would be correct when planning how the project will handle identified threats.

  • ✓

    Obtain formal acceptance from the sponsor

    Why this is correct

    Obtaining formal acceptance from the sponsor satisfies the closure requirement to confirm deliverables meet agreed criteria before releasing resources. This sign-off transfers ownership to the business and authorises final payments, distinguishing closure from ongoing monitoring. Without documented sponsor acceptance, the project cannot be formally closed or lessons learned validated.

  • ✗

    Conduct feasibility study

    Why it's wrong here

    A feasibility study belongs to project initiation, assessing viability before approval, so it cannot be a closure activity. It is tempting because closure does involve evaluating outcomes, and a feasibility study would be correct when deciding whether a proposed project should be authorised at all.

  • ✗

    Create the project charter

    Why it's wrong here

    The project charter is produced during initiation to authorise the project, so creating it at closure is impossible. It is tempting because closure involves formal documentation and sign-off, and a charter would be correct when formally starting a project and granting the manager authority.

  • ✓

    Archive project documents

    Why this is correct

    Archiving project documents preserves the project's historical record for audit, compliance and future reference, satisfying the closure requirement to formally transfer and retain deliverables and records. It ensures organisational process assets are updated once the project ends, supporting lessons-learned reuse and traceability without affecting scope, schedule or cost baselines.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.