PK0-005 Project Life Cycle Practice Question
A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Obtain formal acceptance from the sponsor
During closure, obtaining formal acceptance from the sponsor and archiving project documents are key activities. Releasing resources and contract closure are also part of closure, but the question asks for two. The correct answers are formal acceptance and archiving documents.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Develop the risk register
Why it's wrong here
The risk register is developed during planning.
- ✓
Obtain formal acceptance from the sponsor
Why this is correct
Formal acceptance is a key closure activity.
- ✗
Conduct feasibility study
Why it's wrong here
Feasibility study is done during initiation.
- ✗
Create the project charter
Why it's wrong here
The charter is created during initiation.
- ✓
Archive project documents
Why this is correct
Archiving documents is part of closure.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.