Courseiva

PK0-005 Project Management Concepts Practice Question

During project selection, an organization evaluates multiple projects using financial methods. Which THREE of the following are commonly used financial project selection methods? (Select THREE).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Net Present Value (NPV)

Net Present Value (NPV) is correct because it is a core discounted cash flow method that compares the present value of a project's expected future cash inflows against its initial investment, using a specified discount rate to determine whether the project adds value. Internal Rate of Return (IRR) is correct because it is a financial method that calculates the discount rate at which a project's NPV equals zero, allowing comparison of a project's expected return against the organization's required rate of return or cost of capital. Payback period is correct because it is a commonly used financial selection method that measures how long it takes for cumulative cash inflows to recover the initial investment, helping assess liquidity and risk. Earned Value Management (EVM) is not a project selection method; it is a performance measurement technique used during project execution to integrate scope, schedule, and cost. Resource leveling is not a financial selection method; it is a scheduling technique used to resolve resource over-allocation by adjusting start and finish dates.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Net Present Value (NPV)

    Why this is correct

    NPV discounts all future cash inflows and outflows to present value, then subtracts the initial investment. A positive NPV signals the project adds financial value, making it a standard discounted cash-flow method for comparing and selecting candidate projects during project selection.

  • ✗

    Earned Value Management (EVM)

    Why it's wrong here

    Earned Value Management compares planned value, earned value and actual cost to measure schedule and cost performance during execution; it requires a baselined project, so it cannot appraise competing proposals before selection. It would be correct when the question asks how to track cost and schedule variance on an in-flight project.

  • ✓

    Internal Rate of Return (IRR)

    Why this is correct

    IRR calculates the discount rate at which a project's NPV equals zero, expressing expected return as a percentage. Comparing that rate against the organisation's cost of capital lets selectors rank projects, satisfying the financial selection criterion in the stem.

  • ✗

    Resource leveling

    Why it's wrong here

    Resource levelling adjusts task start and finish dates to smooth demand for constrained resources; it is a scheduling technique, not a financial appraisal method, so it produces no ROI, NPV or payback figure for ranking candidate projects. It would be the right answer when the question asks how to resolve resource overallocation within an approved schedule.

  • ✓

    Payback period

    Why this is correct

    Payback period measures how long cumulative cash inflows take to recover the initial investment. It is a straightforward financial selection method, though it ignores the time value of money and cash flows occurring after the break-even point.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.