Courseiva
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

Which of the following is an example of gold plating?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

A developer adds a feature not in the requirements because it would be 'nice to have'

Gold plating is when the project team adds extra features beyond what was required, which can introduce risk and scope creep.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • A developer adds a feature not in the requirements because it would be 'nice to have'

    Why this is correct

    Adding unrequested features is gold plating.

  • A stakeholder requests an additional feature and the PM rejects it

    Why it's wrong here

    Rejecting a request is not gold plating.

  • The team removes a feature to meet the deadline

    Why it's wrong here

    This is scope reduction, not gold plating.

  • A developer adds a user-requested feature that was approved through change control

    Why it's wrong here

    This is a legitimate change, not gold plating.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.