Tools and Documentation →easyMultiple Choice

PK0-005 Tools and Documentation Practice Question

Which project document formally authorizes the project and identifies the project manager?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project charter

The project charter is the document that formally authorizes the project and gives the project manager authority.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Business case

    Why it's wrong here

    The business case justifies the investment by comparing benefits, costs and risks, but it is an input that precedes approval and carries no authorising authority. It is tempting because it triggers the project, yet the project charter is what formally authorises the work and names the project manager.

  • ✓

    Project charter

    Why this is correct

    The project charter formally authorises the project's existence and explicitly identifies the assigned project manager, conferring authority to proceed. It satisfies both constraints in the stem, whereas subsidiary documents such as the project management plan assume authorisation already exists.

  • ✗

    Project management plan

    Why it's wrong here

    The project management plan describes how the project will be executed, monitored and controlled; it is produced after authorisation and does not grant it. It is tempting as the overarching governing document, yet the project charter is the artefact that formally authorises the project and identifies the project manager.

  • ✗

    Scope statement

    Why it's wrong here

    The scope statement documents deliverables, boundaries and acceptance criteria; it neither authorises the project nor names the project manager. It is tempting because it is a foundational planning document, but authorisation belongs to the project charter, which the sponsor signs to formally empower the manager.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.