In a matrix organization, a project manager needs to acquire a team member from a functional department. The functional manager is reluctant to release the resource due to other work. What is the best way for the project manager to address this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Negotiate with the functional manager for the resource

In a matrix organization, the PM must negotiate with the functional manager for resources.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Negotiate with the functional manager for the resource

    Why this is correct

    In a matrix organisation, resources remain under functional manager control, so the project manager must negotiate directly with that manager to secure the team member. Negotiation addresses the shared-authority constraint rather than escalating or demanding the resource.

  • ✗

    Hire an external contractor

    Why it's wrong here

    Contracting bypasses the functional manager entirely, spending budget and adding onboarding delay while leaving the matrix authority conflict unresolved. Tempting when internal negotiation stalls, but escalation and resource negotiation within the matrix is the expected route; contractors suit genuine skill gaps, not temporary contention.

  • ✗

    Assign the task to another team member

    Why it's wrong here

    Reassigning the task avoids the resourcing conflict rather than resolving it, and may exceed remaining team capacity or skills. It is tempting when the deliverable must proceed regardless, but this option is correct only when the required expertise already exists elsewhere and the schedule permits the substitution.

  • ✗

    Escalate to the project sponsor immediately

    Why it's wrong here

    Escalation bypasses the negotiation the matrix structure expects the project manager to attempt first, and sponsors typically reject premature escalation. It is tempting because sponsors can arbitrate cross-functional disputes, making escalation correct only after direct negotiation with the functional manager has genuinely failed.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.